Throughout 2024, Ventro has hosted quarterly, industry-leading webinars on key topics. In our October 2024 session, titled "Fire Safety Insights: Building Control, Procurement Law, and the Grenfell Inquiry," we had the privilege of featuring Josh Paulin from the Building Safety Regulator (BSR). Josh delivered an outstanding presentation covering the latest updates introduced by the Building Safety Act, with a particular focus on the BSR’s building control functions and common issues encountered in Gateway applications. While we couldn’t address all questions in detail during the live event, we’re grateful that Josh took the time to answer the remaining queries. You can find his responses below.
Operational Policy Advisor, Building Safety Regulator
Josh Paulin has worked in operational policy and operational delivery for a number of years. Having originally trained as a scientist, he has worked within the NHS, in public policy for the New Zealand Government, before joining the Building Safety Regulator (BSR) as an Operational Policy Advisor in 2023.
Within BSR he has worked on resident engagement policy for the in-occupation team, focusing on helping industry understand the new resident engagement duties introduced by the Building Safety Act. Now as a member of the building control team he helps BSR’s operational teams with interpretation of the legislation and regulations, and regularly engages with industry to help inform about expectations within the new regulator.
It depends on what you mean by fire strategy, but there are various legal requirements within a HRB. Examples include the need for building work within a HRB to meet the functional requirements of Part B of the Building Regulations, and for building control approval applications to provide documents such as a fire and emergency file as part of the application. Furthermore, as part of the Building Assessment Certificate process under Part 4 of the Building Safety Act, Principle Accountable Persons would be expected to articulate how they manage any building safety risks, including the risk of spread of fire, within a HRB. All of these would reference and potentially include details of the fire strategy for the HRB.
As discussed in the webinar, Regulation 10 of The Building (Higher-Risk Buildings Procedures)(England) Regulations 2023 allows for emergency repairs that meets the definition of building work to take place prior to building control approval being received, if the emergency repairs is needed as a matter of urgency and not doing so would be a risk to health, safety or welfare of persons in or around the building. It is not intended as a route to circumvent the building control process. An important consideration when considering whether work would count as an emergency repair under regulation 10, is whether the risk can be adequately managed while going through the normal building control process.
If regulation 10 is used, then BSR needs to be notified that emergency repairs are taking place, and a regularization application needs to be made to BSR once the works are carried out. BSR will review the appropriateness of the use of regulation 10 at both of these points.
Another team in BSR would be best placed to give you a full answer on this, if you could use Contact the Building Safety Regulator - GOV.UK your query will be passed to the right team.
The application process for Cat A and Cat B works are the same, an application has to be made as per Regulation 12 of The Building (Higher-Risk Buildings Procedures) (England) Regulations 2023. The documentation required to be submitted differs however and is outlined in the above regulation.
New build and occupied HRB building control applications come through the same portal and are processed by the same operational teams. There are currently no plans to review or change this.
Please see this guidance (Operating a mandatory occurrence reporting system - GOV.UK) for a detailed answer.
Category A and Category B works refer to building work in an occupied HRB and refer to the type of work taking place. More substantial works will often class as Category A (such as work affecting the active or passive fire safety measures in the HRB), with more minor work being likely to be Category B. Please see Regulation 12 of The Building (Higher-Risk Buildings Procedures) (England) Regulations 2023 for a full definition.
BSR welcomes competent persons schemes to be used for building work where appropriate to do so, but we are unaware of any that would cover work to fire doors in HRBs. If one was to be set up that would cover this work, then we would treat it in the same way as any competent person scheme work.
It would depend upon who they are advising.
BSR has duties as a Building Control Authority (BCA), and in discharging its’ duty as the BCA, BSR will appoint a multi-disciplinary team to provide support in reaching a determination. A RBI registered to the right classification with BSR and competent for the work, is able to undertake restricted activities and advise on restricted functions. The regulator must seek the advice of an RBI before undertaking a restricted function.
If you are referring to duties under Part 2 of The Building Regulations 2010, then yes, if the RBI provides advice to an applicant that could meet the definition of “design work” then they would have the legal duties of a designer.
If the regularisation application for the work carried out as emergency repairs is rejected for any reason, then a normal building control approval application may be required if additional building work is needed to be carried out, or another regularization application may be required to cover the emergency works. It would depend on the case, and BSR would possibly meet with you to discuss the best next steps.
As discussed in the webinar, the overwhelming reason building control applications are being rejected is because they do not contain enough information for BSR to make an assessment on the application. We are engaging with applicants (by having webinars such as this for example) to try and help improve applications to counter this. Also considering resident safety, the Part 4 duties under the Building Safety Act mean that the Principle Accountable Person for a HRB need to apply for a Building Assessment Certificate to in part, show how they manage building safety risks in their building. Therefore, there are multiple regimes trying to improve resident safety.
The decision to not provide pre-application advice is based on the recommendations of the Independent Review of Building Regulations and Fire Safety: Hackitt review.
The best place to start is ascertaining whether the proposed project, or any part of the proposed project, meets the definition of building work as defined in Regulation 3 of The Building Regulations 2010. In making this judgement, we would always suggest seeking professional advice.
BSR has the ability to use any RBIs irrespective of their employer, when forming an MDT. Multiple factors are being worked on to improve our application processing times.
Cladding remediating works are being prioritised.
If building work affects passive fire stopping measures such as the internal fire stopping, then it is possible this would count as building work and need a building control application. As you state, if it affects passive fire safety measures then it could classify as Category A work. It would be best to seek professional advice to help determine if the work you intend to carry out would count as building work.
If building work affects passive fire stopping measures such as the internal fire stopping, then it is possible this would count as building work and need a building control application. As you state, if it affects passive fire safety measures then it could classify as Category A work. It would be best to seek professional advice to help determine if the work you intend to carry out would count as building work.
I cannot give a figure for the average Gateway 3 processing time unfortunately.
BSR is aware of this tribunal outcome, and we are taking necessary steps to establish the effects this could have on BSR and its operations.
Fire doors play an integral part in passive fire stopping within a building. BSR considers the full replacement of a fire door to be building work and requires a building control application.
BSR works closely with partner regulators including the FRS, but we are bound by the legislations and regulations and must follow these processes when assessing building control approval applications.
BSR recently ran a residents' campaign (Your home, your safety - Making Buildings Safer) which provides some information on residents' duties, and we are working with the Ministry of Housing, Communities and Local Government to develop further guidance for residents to help understand their responsibilities when carrying out building work in their properties.
Both the building control approval (Gateway 2) and completion certificate applications (Gateway 3) processes are integral to how BSR carries out its function as a Building Control Authority in HRBs.
The central question is whether the work you are planning to carry out would meet the definition of building work as defined in Regulation 3 of the Building Regulations 2010. If so, then a building control approval application would be required, unless the work is exempt work (as defined in Schedule 2 of The Building (Higher-Risk Buildings Procedures) (England) Regulations 2023) or wholly scheme work (as defined in Schedule 3 of the Building Regulations 2010). It is worth noting that minor repairs, such as replacing light bulbs, are unlikely to meet the definition of building work, but it is possible replacing whole emergency lighting systems could count. As always, seeking professional advice is advised.
Please use the Contact the Building Safety Regulator - GOV.UK service, for this to be looked into.
I’m not sure what this question is specifically referring to, but please see previous answers on fire doors, and how to determine whether a building control approval application is required.
BSR does have a resident engagement team, and if you use the Contact the Building Safety Regulator - GOV.UK service, this team should be able to look into this further.
A lot would come down to perceived intent. We want people to use the emergency repair process when appropriate. If the case is reviewed and not deemed an emergency, then we would engage with the applicant to determine the next steps, but it is an offence under section 35 of The Building Act to contravene building regulations.
Please see previous answer regarding fire doors.
Again, the central question would be whether the additional works met the definition of building work as defined in Regulation 3 of the Building Regulations 2010. But it is worth noting that it is an offence to carry out building work prior to a building control approval application being approved.